CH-640 Fuselage Front Z and torque tube tunnel (17 of 70)




Center the floor Z to the front of the assembly, flush to the bottom of the side walls.  Mark the location of the side walls on the floor z.  Measure up 12 mm then 25 mm for A5 rivets.  Drill these now.
Center the floor Z to the front of the assembly, flush to the bottom of the side walls. Mark the location of the side walls on the floor z. Measure up 12 mm then 25 mm for A5 rivets. Drill these now.